The progress continues on the new Shore Physical Education Centre (SPEC). .

Current Activities:

  • Excavation works are complete
  • Foundation works for the pool hall are complete and the lower ground floor structure works are continuing.
  • Installation of in ground services are nearing completion within the main site.
  • Major concrete pours have commenced and will continue until the second quarter of 2019.
  • The lower ground pool walls and rainwater tank are nearing completion.
  • The delivery of precast columns, panels and steel will commence during November / December 2018.

Next Steps:

  • Delivery of structural steel members for onsite preassembly using over 9000 bolts, in spans exceeding 30 metres in length.
  • These will be erected between the pre-cast columns from January 2019 to form the support structure for the classrooms and landscaped terracing.