SPEC Update – August

SPEC Update – August

An important milestone in the SPEC project was reached on Tues 20 August, with Dr Wright, Mr Morrison and Chair of School Council – Rev Stuart Holman, invited to ‘top-out’ the construction.

Current Status

Pool Hall:

  • The pool structure is complete and the ETFE roof (a transparent pressurised roofing system) is installed and inflated.
  • Face brickwork and glazing are installed.
  • The planter boxes on the landscaped terrace above the pool hall are poured.
  • Fitout, services roughing in, blockwork and partition wall installation are continuing.

Sports Hall:

  • The Level 3 floor for the Christian Studies classrooms is poured.
  • Roofing installation for Level 3 has commenced.
  • Fitout, services roughing in, blockwork and partition wall installation are continuing.

Car Park:

  • Structure is complete including landscape structures on the roof.

Robson Courtyard:

  • Preparation for pouring the concrete slab on the ground and the tiered seating is underway.

Next Steps

  • The pouring of Level 4 of the Sports Hall by 20 August 2019 will complete the concrete and steel structure on the site.
  • Tiling of the pool.
  • Façade works to the PDHPE classrooms above the pool.
  • In the car park, stripping of formwork and commencing fitout.
  • Crane to be dismantled in mid-September 2019.